Things are progressing quickly at Beach Houses!

Things are progressing quickly at Beach Houses! Over the past few weeks, the construction team has successfully installed the model home’s below slab drainage, the ground floor slab and completed the majority of the block work of the walls. They are now in the process of erecting the formwork for the roof structure. In the coming days, the majority of the roof formwork will be in place and reinforcement will have commenced.